Tag Archives: Menard’s

And the Color is…

Leelanau County – July 26, 2019Written by Jim

As we were finishing up the barn last year, we started picking out colors for this year’s cabin project. We had always intended to tie the two buildings together by accenting them both with the Wicker shakes in the gable ends and the wide white PVC trim, but we wanted each to have an independent field color. We had settled on a horizontal taupe, and even painted the shed doors to match.

Well, the pandemic-affected supply chain had other ideas…

It turns out that taupe pigment was not available to make our siding, so we had to come up with a Plan B. Time to get creative! Our supplier actually suggested the Certainteed brand of siding for availability, which Menards just happened to also carry at a much cheaper price. Lop another 11% off of that with their summer-long rebate sale and they practically gave us the siding! So what color did we choose?

Pacific Blue!

We are happy with the way it looks with the barn. One side done, three to go!

This past week has been a mix of working on the siding and other projects that have to be buttoned up before the insulation and drywall crews arrive. Two of the four insulation crews have come and gone, along with the electrician. The electrical inspector approved the rough electrical and the building inspector approved the rough framing. We are good to go!

Down in the crawl space, I was able to put the top 9” of foam board up along with the silver seam tape. Once the HVAC, plumbing and electric finish work is completed in this area, we will put a reinforced white liner on the floor. The foam board, liner and rim joist insulation are what make up a ‘conditioned’ crawl space, which is required by Michigan building code.

As much pre-planning as we did, some things came up that required some quick thinking. Placing backing to mount the vanity lights and mirrors were one thing we hadn’t considered. A rainy day trip to Menards to pick out the mirror and lights gave us the measurements we needed to mount the backing board.

While we were there, we decided on our porch ceiling, as that needs to be done before we can put the siding up on that wall. I’m on the upper level of the wood storage rack getting ready to hand down 32 pieces of wood to Diana in this photo. We chose 1 x 6 pine carsiding that we will finish with a clear spar urethane. Stay tuned to see how that comes out.

We also realized that building a shower niche requires knowing the measurements of the tile that will surround it. After picking out our tile, we decided on the size and placement of the niches in our bathrooms.

Here is the one in our main bathroom. I have to wait until the outside wall is insulated before I can put up the rest of the cement board in this room.

Our master shower cement board is nearly complete, as these are all inside walls. I will trim out the niches in both baths when the drywall behind them is installed.

This past weekend, we bid a Leelanau farewell to our friends Rod and Mary, as they sold their cottage here and will be living full time in their Florida home.

Patti and Lane arranged an evening at The Ridge at Verterra Winery and then dinner at Nittolo’s in Lake Leelanau. From right to left: Mary & Rod, Paul & JoAnn, Lane & Patti and the two of us. We all met at Wild Cherry Resort back in 2015. We sure are going to miss having Rod and Mary here, as well as their dog Gracie. Fortunately, we will catch up with them in Florida!

Our friends Terry and Diane also stopped by with their grandson on their way north to the Upper Peninsula to go fishing. It was good to see them again!

Stay tuned for our next post where we will hopefully have insulation and drywall installed, as well as more siding. Until then, safe and happy travels to all!

Up it goes!

Leelanau County, Michigan – Saturday, May 29 – Written by Jim

Our cabin has begun rising from the foundation!

©️2009 Disney/Pixar

Well, not quite like that, but we do have progress to report! Our framers showed up this week and went at it in earnest. Prior to their arrival, I took the opportunity to insulate the lower four feet of the crawl space.

Getting this much done while standing straight up made life a lot easier. The insulation is two pieces of 1-1/2” thick polyiso board. Putting it up was a fairly simple process:

Drill a hole with a 5” long masonry bit.
Insert the 4-1/2” masonry fastener.
Tap it with a rubber mallet until it is tight.

The top part of the insulation will be finished once the floor joists are mounted to the top of the crawl space wall. I will also use aluminum tape to seal the joints in the foam board. Time for me to stand back and watch the framers build!

Ryan, Paul and Richard dove right into it. First thing they did was to assemble the center beam and support it with posts. Then came the treated wood sill plate on top of the foundation walls, along with a foam strip of sill sealer between them. The sill plate is attached to the block wall below with anchor bolts that the mason set into concrete. Follow that with the I-joists that span the entire width of the cabin and the rim joist around the outside.

It was then time for me to get back in the action. With us getting our material weeks earlier, I stored all of that high-priced OSB flooring in the barn. We purchased pallet forks for the front of our tractor last year and I was able to bring out several sheets at a time. They mentioned how it really helped them speed things up. Speaking of high priced lumber: This time last year, a sheet of 3/4” subfloor like this was in the $17 range. We purchased it in March at Menard’s for less that $30 a sheet. We thought that was crazy. Well, it is a good thing we bought it when we did, as we had to purchase two additional sheets to finish the floor. The price? A whopping $72 a sheet!

The crawl space is getting dark down there. Other than whatever comes through the hatch in the center of the cabin, that space hopefully won’t see daylight for a long time! By noon the next day, the floor was complete.

As the framers started building the walls, Adam from Peninsula Excavating started backfilling. He worked all afternoon and an hour the next morning to level things out. We had some steep areas below the cabin that were difficult to mow, so he used the extra dirt to soften them. It really came out nice.

By the end of the day, we had a wall!

The next day, they assembled the opposite wall in two sections. Here is a video of one of those going up. They use an electric wall jack to raise it. You can also see these clamp-on forks on my tractor bucket.

They had me push the button on the second half, as Ryan had to be by the wall joint to finesse the two together. That was fun!

Once they completed that, they framed an end wall until the end of the day and called it a week. They will be back on Tuesday.

Even the beams for our covered entry are in place! They can be seen extending out from the wall on the left side of the photo.

This morning, we had to go to Lowe’s to pick up our flooring. As we were getting in the truck, we heard a roar through the trees:

A hot air balloon! Looks like our cabin isn’t the only thing going up in Leelanau County. 😊

That’s our update for now. Stay tuned to see how much the framers get done next week. Until then, safe and happy travels to all!